Soosaiya Anthreas
Project Execution of Mega-Projects for the Oil and Gas Industries
Soosaiya Anthreas
Project Execution of Mega-Projects for the Oil and Gas Industries
- Gebundenes Buch
- Merkliste
- Auf die Merkliste
- Bewerten Bewerten
- Teilen
- Produkt teilen
- Produkterinnerung
- Produkterinnerung
This book covers execution of mega industrial projects in oil/gas industries covering engineering, procurement, construction, commissioning and performance testing and covers various tasks under each discipline to define the detailed scope of work, supplies and services.
Andere Kunden interessierten sich auch für
- Soosaiya AnthreasProject Execution of Mega-Projects for the Oil and Gas Industries71,99 €
- Kelvin HughesUnderstanding the NEC3 ECC Contract63,99 €
- Kelvin HughesUnderstanding the NEC4 ECC Contract174,99 €
- Kelvin HughesUnderstanding the NEC4 ECC Contract45,99 €
- Understanding Data Analytics and Predictive Modelling in the Oil and Gas Industry122,99 €
- Robert ButtrickThe Project Workout81,99 €
- Dennis LockThe Essentials of Project Management55,99 €
-
-
-
This book covers execution of mega industrial projects in oil/gas industries covering engineering, procurement, construction, commissioning and performance testing and covers various tasks under each discipline to define the detailed scope of work, supplies and services.
Hinweis: Dieser Artikel kann nur an eine deutsche Lieferadresse ausgeliefert werden.
Hinweis: Dieser Artikel kann nur an eine deutsche Lieferadresse ausgeliefert werden.
Produktdetails
- Produktdetails
- Verlag: Taylor & Francis Ltd
- Seitenzahl: 208
- Erscheinungstermin: 24. März 2021
- Englisch
- Abmessung: 161mm x 241mm x 19mm
- Gewicht: 462g
- ISBN-13: 9780367675257
- ISBN-10: 0367675250
- Artikelnr.: 60606033
- Verlag: Taylor & Francis Ltd
- Seitenzahl: 208
- Erscheinungstermin: 24. März 2021
- Englisch
- Abmessung: 161mm x 241mm x 19mm
- Gewicht: 462g
- ISBN-13: 9780367675257
- ISBN-10: 0367675250
- Artikelnr.: 60606033
SECTION I PLANNING AND EXECUTION IN LEVEL 3. 1. Management, Control and
Administration. 2. HSE, Social and Security. 3. Services and Facilities to
Owner. 4. Engineering. 5. Procurement and Supply. 6. Transport, Logistic
and Storage. 7. Construction. 8. Pre-Commissioning. 9. Commissioning,
Start-up and Performance Test. 10. Temporary Facilities. SECTION II
COMMERCIAL ASPECTS. 11. Commencement Date and Effective Dates. 12.
Extension of Time. 13. Professionally Handling Large Claims. 14.
Prolongation and Disruption Costs. 15. Penalty/Interest for Payment Delays.
16. Force Majeure. 17. Concurrent Delays. 18. Hedging against Currency
Fluctuations. 19. Indemnity. 20. Consequential, Indirect Damages. 21. Laws
and Regulations. 22. Escalation. 23. Liens. 24. Total Liability. 25.
Payment Terms. 26. Planning. 27. Progress Measurement. 28. EOT claim. 29.
Interpretation Rules. 30. Change/Variations/Trend Notices. 31. Contract
Price below Floor Price and Consequences. 32. Owner's Delay on Document
Approval. 33. Insurances. SECTION III TECHNICAL ASPECTS. 34. Life Cycle
Cost Analysis (LCCA). 35. Consequences of Delayed Rigless Test on Wells
(Owner Delays). 36. Strategy for using Non-Spec Feedstock for
Commissioning. 37. Gas In and Authority Check points. 38. Value
Engineering. 39. Design Defect, Construction Defect and Damages. 40. NDT
(Non-Destructive Testing). 41. Destructive Testing. 42. Hydrostatic Leak
Test. 43. Heavy Lift Load Sharing for Cranes. SECTION IV GLOSSARY OF
ABBREVIATIONS, NAMES AND MEANING. APPENDIX. 1. Project Organization. 2.
Contract Price Weight Factor. 3. Monthly Status Report Contents. 4.
Material Requisition Cycle(MR). 5. FEED Deliverable List. 6. Process Block
Flow Diagram. 7. Document Categories. 8. Claims and Liens Release Letter.
9. Prolongation and Disruption Cost: Hudson formula. 10. A typical list of
Procedures and Plans. 11. Total Plant Break down into Areas.
Administration. 2. HSE, Social and Security. 3. Services and Facilities to
Owner. 4. Engineering. 5. Procurement and Supply. 6. Transport, Logistic
and Storage. 7. Construction. 8. Pre-Commissioning. 9. Commissioning,
Start-up and Performance Test. 10. Temporary Facilities. SECTION II
COMMERCIAL ASPECTS. 11. Commencement Date and Effective Dates. 12.
Extension of Time. 13. Professionally Handling Large Claims. 14.
Prolongation and Disruption Costs. 15. Penalty/Interest for Payment Delays.
16. Force Majeure. 17. Concurrent Delays. 18. Hedging against Currency
Fluctuations. 19. Indemnity. 20. Consequential, Indirect Damages. 21. Laws
and Regulations. 22. Escalation. 23. Liens. 24. Total Liability. 25.
Payment Terms. 26. Planning. 27. Progress Measurement. 28. EOT claim. 29.
Interpretation Rules. 30. Change/Variations/Trend Notices. 31. Contract
Price below Floor Price and Consequences. 32. Owner's Delay on Document
Approval. 33. Insurances. SECTION III TECHNICAL ASPECTS. 34. Life Cycle
Cost Analysis (LCCA). 35. Consequences of Delayed Rigless Test on Wells
(Owner Delays). 36. Strategy for using Non-Spec Feedstock for
Commissioning. 37. Gas In and Authority Check points. 38. Value
Engineering. 39. Design Defect, Construction Defect and Damages. 40. NDT
(Non-Destructive Testing). 41. Destructive Testing. 42. Hydrostatic Leak
Test. 43. Heavy Lift Load Sharing for Cranes. SECTION IV GLOSSARY OF
ABBREVIATIONS, NAMES AND MEANING. APPENDIX. 1. Project Organization. 2.
Contract Price Weight Factor. 3. Monthly Status Report Contents. 4.
Material Requisition Cycle(MR). 5. FEED Deliverable List. 6. Process Block
Flow Diagram. 7. Document Categories. 8. Claims and Liens Release Letter.
9. Prolongation and Disruption Cost: Hudson formula. 10. A typical list of
Procedures and Plans. 11. Total Plant Break down into Areas.
SECTION I PLANNING AND EXECUTION IN LEVEL 3. 1. Management, Control and
Administration. 2. HSE, Social and Security. 3. Services and Facilities to
Owner. 4. Engineering. 5. Procurement and Supply. 6. Transport, Logistic
and Storage. 7. Construction. 8. Pre-Commissioning. 9. Commissioning,
Start-up and Performance Test. 10. Temporary Facilities. SECTION II
COMMERCIAL ASPECTS. 11. Commencement Date and Effective Dates. 12.
Extension of Time. 13. Professionally Handling Large Claims. 14.
Prolongation and Disruption Costs. 15. Penalty/Interest for Payment Delays.
16. Force Majeure. 17. Concurrent Delays. 18. Hedging against Currency
Fluctuations. 19. Indemnity. 20. Consequential, Indirect Damages. 21. Laws
and Regulations. 22. Escalation. 23. Liens. 24. Total Liability. 25.
Payment Terms. 26. Planning. 27. Progress Measurement. 28. EOT claim. 29.
Interpretation Rules. 30. Change/Variations/Trend Notices. 31. Contract
Price below Floor Price and Consequences. 32. Owner's Delay on Document
Approval. 33. Insurances. SECTION III TECHNICAL ASPECTS. 34. Life Cycle
Cost Analysis (LCCA). 35. Consequences of Delayed Rigless Test on Wells
(Owner Delays). 36. Strategy for using Non-Spec Feedstock for
Commissioning. 37. Gas In and Authority Check points. 38. Value
Engineering. 39. Design Defect, Construction Defect and Damages. 40. NDT
(Non-Destructive Testing). 41. Destructive Testing. 42. Hydrostatic Leak
Test. 43. Heavy Lift Load Sharing for Cranes. SECTION IV GLOSSARY OF
ABBREVIATIONS, NAMES AND MEANING. APPENDIX. 1. Project Organization. 2.
Contract Price Weight Factor. 3. Monthly Status Report Contents. 4.
Material Requisition Cycle(MR). 5. FEED Deliverable List. 6. Process Block
Flow Diagram. 7. Document Categories. 8. Claims and Liens Release Letter.
9. Prolongation and Disruption Cost: Hudson formula. 10. A typical list of
Procedures and Plans. 11. Total Plant Break down into Areas.
Administration. 2. HSE, Social and Security. 3. Services and Facilities to
Owner. 4. Engineering. 5. Procurement and Supply. 6. Transport, Logistic
and Storage. 7. Construction. 8. Pre-Commissioning. 9. Commissioning,
Start-up and Performance Test. 10. Temporary Facilities. SECTION II
COMMERCIAL ASPECTS. 11. Commencement Date and Effective Dates. 12.
Extension of Time. 13. Professionally Handling Large Claims. 14.
Prolongation and Disruption Costs. 15. Penalty/Interest for Payment Delays.
16. Force Majeure. 17. Concurrent Delays. 18. Hedging against Currency
Fluctuations. 19. Indemnity. 20. Consequential, Indirect Damages. 21. Laws
and Regulations. 22. Escalation. 23. Liens. 24. Total Liability. 25.
Payment Terms. 26. Planning. 27. Progress Measurement. 28. EOT claim. 29.
Interpretation Rules. 30. Change/Variations/Trend Notices. 31. Contract
Price below Floor Price and Consequences. 32. Owner's Delay on Document
Approval. 33. Insurances. SECTION III TECHNICAL ASPECTS. 34. Life Cycle
Cost Analysis (LCCA). 35. Consequences of Delayed Rigless Test on Wells
(Owner Delays). 36. Strategy for using Non-Spec Feedstock for
Commissioning. 37. Gas In and Authority Check points. 38. Value
Engineering. 39. Design Defect, Construction Defect and Damages. 40. NDT
(Non-Destructive Testing). 41. Destructive Testing. 42. Hydrostatic Leak
Test. 43. Heavy Lift Load Sharing for Cranes. SECTION IV GLOSSARY OF
ABBREVIATIONS, NAMES AND MEANING. APPENDIX. 1. Project Organization. 2.
Contract Price Weight Factor. 3. Monthly Status Report Contents. 4.
Material Requisition Cycle(MR). 5. FEED Deliverable List. 6. Process Block
Flow Diagram. 7. Document Categories. 8. Claims and Liens Release Letter.
9. Prolongation and Disruption Cost: Hudson formula. 10. A typical list of
Procedures and Plans. 11. Total Plant Break down into Areas.